As part of its Supplier’s QMP, the Phase 3 & 4 Supplier must have a process for the redline marking-up of the For Construction drawing set.
The purpose of the redline drawings it to provide an interim copy of the drawings recording and documenting the exact as-built condition of the site after the works are complete, before the final CAD Asbuiltdrawings are available. The Phase 3 & 4 Supplier is fully responsible for the content of the redline drawings.
The latest version of the For-Construction drawings must be used and are to be marked up neatly by hand in red pen or electronically (e.g. PDF) in red, showing the final as-built arrangement and condition of the site. The redline drawing mark-ups must:
-
document items that have been built correctly to the specified FC Drawing requirement with a redtick () next to the relevant note, drawing detail, dimension, etc;
-
document any changes to the drawings in sufficient detail with dimension, member sizes, bolts spacing & type, etc, so that the Phase 2 Supplier is able to use this information to update the CAD drawings to produce the As-built drawings;
-
cross out any items not built with a red cross
-
as per the requirements in OSD-070, including cross-out all words relating to NEW or PROPOSED and the space after the words. There is no need to replace NEW or PROPOSED with EXISTING.
-
update all text in future tense to present tense, eg, change “INSTALL OPTUS RRU ONPROPOSED NEW MOUNT” to “OPTUS RRU ON MOUNT”
-
not cross out or delete any equipment shown on the drawings that has not been installed. Add the comment “FUTURE EQUIPMENT BY OTHERS”.